Which process must occur after a project manager has been assigned to the project?

Which process must occur after a project manager has been assigned to the project?

PrepAway - Latest Free Exam Questions & Answers

A.
Collect Requirements

B.
Develop the project charter

C.
Develop the project statement of work

D.
Develop project closing document

Explanation:
The Collect Requirements process occurs during project planning. Other options occur during project initiation. Option D is associated with project closing. Collect Requirements is the best option.