The PERT method is MOST used in situations where

The PERT method is MOST used in situations where

PrepAway - Latest Free Exam Questions & Answers

A.
ifIs important to know the inter relationships of activities

B.
Little is known about the cost estimated related to the project

C.
Little experience exists on which to base estimated of activity duration

D.
Resource requirements are well define