PrepAway - Latest Free Exam Questions & Answers

Which of the following are NOT outputs of the Activity Duration Estimation process?

Which of the following are NOT outputs of the Activity Duration Estimation process?

PrepAway - Latest Free Exam Questions & Answers

A.
Activity duration estimates

B.
Schedule baseline

C.
None of the choices are correct

D.
Updates to activity attribute


Leave a Reply