The primary output of the project closing process ____________.

The primary output of the project closing process ____________.

PrepAway - Latest Free Exam Questions & Answers

A.
To formalize and distribute all information pertaining to the project closing

B.
Lessons learned

C.
To get customer and sponsor approval

D.
Milestone list

Explanation:
The primary output of the project closing process is to formalize and distribute all the information pertaining to the closing of the project.