Comparing actual to baseline schedules, examining the statement of work, understanding cost overruns, and assessing risk; all occur during a:
A.
Project audit.
B.
Contract negotiation.
C.
Stakeholder meeting.
D.
Resource leveling activity.
You must be logged in to post a comment.
I have the same idea. A
0
0