PrepAway - Latest Free Exam Questions & Answers

Which of the following would you not consider when developing the activity resource requirements document?

You are a project manager for a small local bank. The bank wants you to design and develop a custom online bill pay software so that its customers can pay their bills online. You are ready to begin the Activity Resource Estimation process for your project. Which of the following would you not consider when developing the activity resource requirements document?

PrepAway - Latest Free Exam Questions & Answers

A.
Resource availability

B.
Project management plan

C.
Resource breakdown structure

D.
Activity list

One Comment on “Which of the following would you not consider when developing the activity resource requirements document?


Leave a Reply