Which of the following techniques is used to control the project schedule?

Which of the following techniques is used to control the project schedule?

PrepAway - Latest Free Exam Questions & Answers

A.
Pareto diagram

B.
Performance measurement

C.
Parametric modelling

D.
Statistical sampling

One Comment on “Which of the following techniques is used to control the project schedule?