Which of the following statements is TRUE regarding various Activity Scheduling tools?

Which of the following statements is TRUE regarding various Activity Scheduling tools?

PrepAway - Latest Free Exam Questions & Answers

A.
PDM allows for conditional branching and iteration of activities.

B.
PDM uses activity-on-node (AON) diagramming method.

C.
PDM allows for conditional branching and iteration of activities.

D.
PDM uses analogous methods as an estimation technique.