Which of the following is not a part of the project cost baseline but is included in the project budget?

Which of the following is not a part of the project cost baseline but is included in the project budget?

PrepAway - Latest Free Exam Questions & Answers

A.
Management Contingency Reserve

B.
Management Overheads

C.
Project Management Planing

D.
Activity Cost Contingency Reserve

Explanation:
The difference between the Cost Baseline and Funding requirement at Project completion is Management Contingency Reserve.
Management Contingency Reserve is not part of project cost baseline.