PrepAway - Latest Free Exam Questions & Answers

Which of the following are parts of project scope management?

Which of the following are parts of project scope management?

PrepAway - Latest Free Exam Questions & Answers

A.
Verify Scope

B.
Collect Requirements

C.
Control Scope

D.
All of the above

Explanation:
There are following processes which are part of Project Scope Management. Collect Requirements Define Scope Create WBS Verify Scope Control Scope

One Comment on “Which of the following are parts of project scope management?


Leave a Reply