Which of the following activities is not part of Plan Risk Management?

Which of the following activities is not part of Plan Risk Management?

PrepAway - Latest Free Exam Questions & Answers

A.
Updating risk register

B.
Determining risk roles and responsibilities

C.
Identifying risk categories

D.
Developing a risk management plan

Explanation:
Updating the risk register first happens in Identify Risks phase. Determining risk roles and responsibilities, Identifying risk categories and developing a risk management plan are part of Plan Risk Management.