Which monitoring or controlling activities would not result in preventive action being applied?

A.
Control Scope
B.
Manage project team
C.
Quality control
D.
Manage Scope statement
Explanation:
Scope, schedule, and Control Costs can all result in corrective action, but not preventive action.
I have the same idea. A