Define Scope involves subdividing the major project deliverables into smaller, more manageable components to __________.

A.
Improve the accuracy of cost, time and resource estimates
B.
Define a baseline for performance measurement and control
C.
Facilitate clear responsibility assignments
D.
All of the above
Explanation:
Define Scope involves subdividing the major project deliverables into smaller, more manageable components to: Improve the accuracy of cost, time and resource estimates. Define a baseline for performance measurement and control. Facilitate clear responsibility assignments.