A scope management plan describes __________.
A.
An assessment of the stability of the stakeholder environment
B.
A highly detailed approach to managing the work breakdown structure scope
C.
How the project scope will be managed and how scope changes will be integrated into the project
D.
The stakeholder’s expectation on how changes will be identified and by what priority they will be addressed
I agree with the answer. C