Which risk response can you choose that will also cause you to update the human resource management plan?

You work as a project manager for BlueWell Inc. Your project is running late and you must

respond to the risk. Which risk response can you choose that will also cause you to update
the human resource management plan?

PrepAway - Latest Free Exam Questions & Answers

A.
Fast tracking the project

B.
Teamingagreements

C.
Crashing the project

D.
Transference