You work as a project manager for TechSoft Inc. You, the project team, and the key project
stakeholders have completed a round of quantitative risk analysis. You now need to update
the risk register with your findings so that you can communicate the risk results to the
project stakeholders – including management. You will need to update all of the following
information except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk distributions within the project schedule

B.
Probabilistic analysis of the project

C.
Probability of achieving cost and time objectives

D.
Trends in quantitative risk analysis