You are the project manager of QSL project for your organization. You are working you’re
your project team and several key stakeholders to create a diagram that shows how various
elements of a system interrelate and the mechanism of causation within the system. What
diagramming technique are you using as a part of the risk identification process?

PrepAway - Latest Free Exam Questions & Answers

A.
System or process flowcharts

B.
Predecessor and successor diagramming

C.
Cause and effect diagrams

D.
Influence diagrams