Which risk response will likely cause a project to use the procurement processes?

You work as a project manager for BlueWell Inc. You are working with your team members
on the risk responses in the project. Which risk response will likely cause a project to use

the procurement processes?

PrepAway - Latest Free Exam Questions & Answers

A.
Acceptance

B.
Mitigation

C.
Exploiting

D.
Sharing