PrepAway - Latest Free Exam Questions & Answers

What will be Neil’s reply to Tom?

Neil works as a project manager for SoftTech Inc. He is working with Tom, the COO of his
company, on several risks within the project. Tom understands that through qualitative
analysis Neil has identified many risks in the project. Tom’s concern, however, is that the
priority list of these risk events are sorted in “high-risk,” “moderate-risk,” and “low-risk” as
conditions apply within the project. Tom wants to know that is there any other objective on
which Neil can make the priority list for project risks. What will be Neil’s reply to Tom?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk may be listed by the responses inthe near-term

B.
Risks may be listed by categories

C.
Risks may be listed by the additional analysis and response

D.
Risks may be listed by priority separately for schedule, cost, and performance


Leave a Reply