Where can Mark determine the priority of a risk given its probability and impact?

Mark is the project manager of the BFL project for his organization. He and the project team
are creating a probability and impact matrix using RAG rating. There is some confusion and
disagreement among the project team as to how a certain risk is important and priority for
attention should be managed. Where can Mark determine the priority of a risk given its
probability and impact?

PrepAway - Latest Free Exam Questions & Answers

A.
Look-up table

B.
Risk management plan

C.
Project sponsor

D.
Risk response plan