Tracy is the project manager of the NLT Project for her company. The NLT Project is
scheduled to last 14 months and has a budget at completion of $4,555,000. Tracy’s
organization will receive a bonus of $80,000 per day that the project is completed early up
to $800,000. Tracy realizes that there are several opportunities within the project to save on
time by crashing the project work. Crashing the project is what type of risk response?

PrepAway - Latest Free Exam Questions & Answers

A.
Enhance

B.
Transference

C.
Exploit

D.
Mitigation