PrepAway - Latest Free Exam Questions & Answers

What component of the change management system is responsible for evaluating, testing, and documenting changes

What component of the change management system is responsible for evaluating, testing,
and documenting changes created to the project scope?

PrepAway - Latest Free Exam Questions & Answers

A.
Configuration Management System

B.
Project Management InformationSystem

C.
Scope Verification

D.
Integrated Change Control


Leave a Reply