PrepAway - Latest Free Exam Questions & Answers

What risk response has management asked Harry to implement?

Harry is the project manager of the MMQ Construction Project. In this project Harry has
identified a supplier who can create stained glass windows for 1,000 window units in the
construction project. The supplier is an artist who works by himself, but creates windows for
several companies throughout the United States. Management reviews the proposal to use
this supplier and while they agree that the supplier is talented, they do not think the artist
can fulfill the 1,000 window units in time for the project’s deadline. Management asked
Harry to find a supplier who will guarantee the completion of the windows by the needed
date in the schedule. What risk response has management asked Harry to implement?

PrepAway - Latest Free Exam Questions & Answers

A.
Acceptance

B.
Transference

C.
Avoidance

D.
Mitigation


Leave a Reply