Which risk management process can satisfy management’s objective for your project?

You work as a project manager for BlueWell Inc. You are working on a project and the
management wants a rapid and cost-effective means for establishing priorities for planning
risk responses in your project. Which risk management process can satisfy management’s
objective for your project?

PrepAway - Latest Free Exam Questions & Answers

A.
Qualitative risk analysis

B.
Quantitative analysis

C.
Historical information

D.
Rolling wave planning