PrepAway - Latest Free Exam Questions & Answers

What should Jenny do with these risk events?

Jenny is the project manager for the NBT projects. She is working with the project team and
several subject matter experts to perform the quantitative risk analysis process. During this
process she and the project team uncover several risks events that were not previously
identified. What should Jenny do with these risk events?

PrepAway - Latest Free Exam Questions & Answers

A.
The events should be determined if they need to be accepted or responded to.

B.
The events should be entered into qualitative risk analysis.

C.
The events should continue on with quantitative risk analysis.

D.
The events should be entered into the risk register.


Leave a Reply