PrepAway - Latest Free Exam Questions & Answers

What risk response is the most appropriate for this instance?

Rob is the project manager of the IDLK Project for his company. This project has a budget
of $5,600,000 and is expected to last 18 months. Rob has learned that a new law may affect
how the project is allowed to proceed – even though the organization has already invested
over $750,000 in the project. What risk response is the most appropriate for this instance?

PrepAway - Latest Free Exam Questions & Answers

A.
Transference

B.
Acceptance

C.
Mitigation

D.
Enhance


Leave a Reply