When will the quantitative risk analysis process need to be repeated?

Fred is the project manager of the PKL project. He is working with his project team to
complete the quantitative risk analysis process as a part of risk management planning. Fred
understands that once the quantitative risk analysis process is complete, the process will
need to be completed again in at least two other times in the project. When will the
quantitative risk analysis process need to be repeated?

PrepAway - Latest Free Exam Questions & Answers

A.
Quantitative risk analysisprocess will be completed again after the plan risk
response planning and as part of procurement.

B.
Quantitative risk analysis process will be completed again after the cost
managementplanning and as a part of monitoring and controlling.

C.
Quantitativerisk analysis process will be completed again after new risks are
identified and as part of monitoring and controlling.

D.
Quantitative risk analysis process will be completed again after the risk response
planning and as a part of monitoring and controlling.