PrepAway - Latest Free Exam Questions & Answers

What approach can Amy take to create a bias against risks that will affect the schedule of the project?

Amy is the project manager for her company. In her current project the organization has a
very low tolerance for risk events that will affect the project schedule. Management has

asked Amy to consider the affect of all the risks on the project schedule. What approach can
Amy take to create a bias against risks that will affect the schedule of the project?

PrepAway - Latest Free Exam Questions & Answers

A.
She can have the project team pad their time estimates to alleviate delays in the
project schedule.

B.
She can shift risk-laden activities that affect the project schedule from the critical
path as much as possible.

C.
She can create an overall project rating scheme to reflect the bias towards risks
that affect the project schedule.

D.
She can filter all risks based on their affect on schedule versus other project
objectives.


Leave a Reply