What project management plan is most likely to direct the quantitative risk analysis process for a project in

What project management plan is most likely to direct the quantitative risk analysis process
for a project in a matrix environment?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk management plan

B.
Human resource management plan

C.
Staffing management plan

D.
Risk analysis plan