PrepAway - Latest Free Exam Questions & Answers

Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis p

You work as a project manager for BlueWell Inc. You are about to complete the quantitative
risk analysis process for your project. You can use three available tools and techniques to
complete this process. Which one of the following is NOT a tool or technique that is
appropriate for the quantitative risk analysis process?

PrepAway - Latest Free Exam Questions & Answers

A.
Quantitative risk analysis andmodeling techniques

B.
Data gathering and representation techniques

C.
Expert judgment

D.
Organizational process assets


Leave a Reply