PrepAway - Latest Free Exam Questions & Answers

Which of the following risk processes is repeated after the plan risk responses to determine if the overall pr

You are the project manager of the NNN project for your company. You and the project
team are working together to plan the risk responses for the project. You feel that the team
has successfully completed the risk response planning and now you must initiate what risk

process it is. Which of the following risk processes is repeated after the plan risk responses
to determine if the overall project risk has been satisfactorily decreased?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk identification

B.
Qualitative risk analysis

C.
Risk response implementation

D.
Quantitative risk analysis


Leave a Reply