PrepAway - Latest Free Exam Questions & Answers

What should you, the project manager, do with assessment of identified risks in consideration of the attitude

You work as a project manager for BlueWell Inc. You are currently working with the project
stakeholders to identify risks in your project. You understand that the qualitative risk
assessment and analysis can reflect the attitude of the project team and other stakeholders
to risk. Effective assessment of risk requires management of the risk attitudes of the
participants. What should you, the project manager, do with assessment of identified risks in
consideration of the attitude and bias of the participants towards the project risk?

PrepAway - Latest Free Exam Questions & Answers

A.
Document the bias for the risk events and communicate the bias with management

B.
Evaluate and document the bias towards the risk events

C.
Evaluate the bias through SWOT for true analysis of the risk events

D.
Evaluate the bias towards the risk events and correct the assessment accordingly