Which one of the following is a valid response to the identified risk event?

Your project team has identified a project risk that must be responded to. The risk has been
recorded in the risk register and the project team has been discussing potential risk
responses for the risk event. The event is not likely to happen for several months but the
probability of the event is high. Which one of the following is a valid response to the
identified risk event?

PrepAway - Latest Free Exam Questions & Answers

A.
Corrective action

B.
Technical performance measurement

C.
Risk audit

D.
Earned value management