What is the project’s schedule performance index?

You are the project manager of the NNH Project. In this project you have created a
contingency response that the schedule performance index should be less than 0.93. The
NHH Project has a budget at completion of $945,000 and is 45 percent complete though the
project should be 49 percent complete. The project has spent $455,897 to reach the 45
percent complete milestone. What is the project’s schedule performance index?

PrepAway - Latest Free Exam Questions & Answers

A.
-$37,800

B.
0.93

C.
1.06

D.
0.92