PrepAway - Latest Free Exam Questions & Answers

Where should she document the risks associated with this technology so she can track the risk status and respo

Adrian is a project manager for a new project using a technology that has recently been
released and there’s relatively little information about the technology. Initial testing of the
technology makes the use of it look promising, but there’s still uncertainty as to the longevity
and reliability of the technology. Adrian wants to consider the technology factors a risk for
her project. Where should she document the risks associated with this technology so she
can track the risk status and responses?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk register

B.
Project scope statement

C.
Project charter

D.
Risk low-level watch list


Leave a Reply