PrepAway - Latest Free Exam Questions & Answers

Is Eric’s organization liable to pay the ZAS Corporation for the work they have completed so far on the

Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to
complete part of the project work for Eric’s organization. Due to a change request the ZAS
Corporation is no longer needed on the project even though they have completed nearly all
of the project work. Is Eric’s organization liable to pay the ZAS Corporation for the work they
have completed so far on the project?

PrepAway - Latest Free Exam Questions & Answers

A.
No, the ZAS Corporation did not complete all of the work.

B.
It depends on what the termination clause of the contract stipulates.

C.
Yes, the ZAS Corporation did not choose to terminate the contract work.

D.
It depends on what the outcome of a lawsuit will determine.


Leave a Reply