The only output of the perform qualitative risk analysis are risk register updates. When the
project manager updates the risk register he will need to include several pieces of
information including all of the following except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Trends in qualitative risk analysis

B.
Risk probability-impact matrix

C.
Watchlist of low-priority risks

D.
Risks grouped by categories