Why should the project team members be involved in the Identify Risk process?

The Identify Risk process determines the risks that affect the project and document their
characteristics. Why should the project team members be involved in the Identify Risk process?

PrepAway - Latest Free Exam Questions & Answers

A.
They are the individuals that will most likely cause and respond to the risk events.

B.
They are the individuals that will have the best responses for identified risks events within the
project.

C.
They are the individuals that are most affected by the risk events.

D.
They are the individuals that will need a sense of ownership and responsibility for the risk
events.

Explanation:

The project team members should be involved in the risk identification so that they will develop a
sense of ownership and responsibility for the risk events and the associated risk responses.
Identify Risks is the process of determining which risks may affect the project. It also documents
risks’ characteristics. The Identify Risks process is part of the Project RiskManagement knowledge
area. As new risks may evolve or become known as the project progresses through its life cycle,
Identify Risks is an iterative process. The process should involve the project team so that they can
develop and maintain a sense of ownership and responsibility for the risks and associated risk
response actions. Risk Register is the only output of this process.