What is the BEST time to perform post-project review by you and your project development team to access the ef

You are the project manager of GHT project. You want to perform post-project review of your
project. What is the BEST time to perform post-project review by you and your project
development team to access the effectiveness of the project?

PrepAway - Latest Free Exam Questions & Answers

A.
Project is completed and the system has been in production for a sufficient time period

B.
During the project

C.
Immediately after the completion of the project

D.
Project is about to complete

Explanation:

The project development team and appropriate end users perform a post-project review jointly
after the project has been completed and the system has been in production for a sufficient time
period to assess its effectiveness.
Answer C is incorrect. It is not done immediately after the completion of the project as its
effectiveness cannot be measured until the system has been in production for certain time period.
Answer B is incorrect. The post-project review of project for accessing effectiveness cannot be
done during the project as effectiveness can only evaluated after setting the project in process of
production.
Answer D is incorrect. Post-project review for evaluating the effectiveness of the project can only
be done after the completion of the project and the project is in production phase.