PrepAway - Latest Free Exam Questions & Answers

What is the process for selecting and implementing measures to impact risk called?

What is the process for selecting and implementing measures to impact risk called?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk Treatment

B.
Control

C.
Risk Assessment

D.
Risk Management

Explanation:

The process for selecting and implementing measures for impacting risk in the environment is
called risk treatment.
Answer A is incorrect. Risk management is the coordinated activities for directing and controlling
the treatment of risk in the organization.
Answer C is incorrect. The process of analyzing and evaluating risk is called risk assessment.