PrepAway - Latest Free Exam Questions & Answers

Which of the following is the FOREMOST root cause of project risk?

Which of the following is the FOREMOST root cause of project risk?
Each correct answer represents a complete solution. Choose two.

PrepAway - Latest Free Exam Questions & Answers

A.
New system is not meeting the user business needs

B.
Delay in arrival of resources

C.
Lack of discipline in managing the software development process

D.
Selection of unsuitable project methodology

Explanation:

The foremost root cause of project risk is:
A lack of discipline in managing the software development process
Selection of a project methodology that is unsuitable to the system being developed
Answer A is incorrect. The risk associated with new system is not meeting the user business
needs is business risks, not project risk.
Answer B is incorrect. This is not direct reason of project risk.


Leave a Reply