PrepAway - Latest Free Exam Questions & Answers

which one?

During qualitative risk analysis you want to define the risk urgency assessment. All of the following
are indicators of risk priority except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Warning signs

B.
Symptoms

C.
Risk rating

D.
Cost of the project

Explanation:

The cost of the project is not an indicator of risk urgency. The affect of the risk on the overall cost
of the project may be considered, but it is not the best answer.
Answer B is incorrect. Symptoms are an indicator of the risk urgency.
Answer A is incorrect. Warning signs are an indicator of the risk urgency.
Answer C is incorrect. The risk rating can be an indicator of the risk urgency.


Leave a Reply