PrepAway - Latest Free Exam Questions & Answers

Which of the following are included in the risk register?

You are the project manager for TTP project. You are in the Identify Risks process. You have to
create the risk register. Which of the following are included in the risk register?
Each correct answer represents a complete solution. Choose two.

PrepAway - Latest Free Exam Questions & Answers

A.
List of potential responses

B.
List of key stakeholders

C.
List of mitigation techniques

D.
List of identified risks

Explanation:

Risk register primarily contains the following:
List of identified risks: A reasonable description of the identified risks is noted in the risk register.
The description includes event, cause, effect, impact related to the risks identified. In addition to
the list of identified risks, the root causes of those risks may appear in the risk register.
List of potential responses: Potential responses to a risk may be identified during the Identify Risks
process. These responses are useful as inputs to the Plan Risk Responses process.
Answer C is incorrect. Risk register do contain the summary of mitigation, but only after the
applying risk response. Here in this scenario you are in risk identification phase, hence mitigation
techniques cannot be documented at this situation.
Answer B is incorrect. This is not valid content of risk register.
A risk register is an inventory of risks and exposure associated with those risks. Risks are
commonly found in project management practices, and provide information to identify, analyze,
and manage risks. Typically a risk register contains:
A description of the risk
The impact should this event actually occur
The probability of its occurrence
Risk Score (the multiplication of Probability and Impact)
A summary of the planned response should the event occur
A summary of the mitigation (the actions taken in advance to reduce the probability and/or impact
of the event) Ranking of risks by Risk Score so as to highlight the highest priority risks to all
involved.


Leave a Reply