PrepAway - Latest Free Exam Questions & Answers

What are the immediate steps you should follow, after planning for risk response process?

You are the project manager of GHT project. You and your team have developed risk responses
for those risks with the highest threat to or best opportunity for the project objectives. What are the
immediate steps you should follow, after planning for risk response process? Each correct answer
represents a complete solution. Choose three.

PrepAway - Latest Free Exam Questions & Answers

A.
Updating Project management plan and Project document

B.
Applying controls

C.
Updating Risk register

D.
Prepare Risk-related contracts

Explanation:

The risk register is updated at the end of the plan risk response process with the information that
was discovered during the process. The response plans are recorded in the risk register.
Project management plan consisting of WBS, schedule baseline and cost performance baseline
should be updated. After planning risk response process, there may be requirementof updating
project documents like technical documentation and assumptions, documented in the project
scope statement.
If risk response strategies include responses such as transference or sharing, it may be necessary
to purchase services or items from third parties. Contracts for those services can be prepared and
discussed with the appropriate parties.
Answer B is incorrect. Controls are implemented in the latter stage of risk response process. It is
not immediate task after the planning of risk response process, as updating of several documents
is done first.
The purpose of the Plan Risk Responses process is to develop risk responses for those risks with
the highest threat to or best opportunity for the project objectives. The Plan Risk Responses
process has four outputs:
Risk register updates
Risk-related contract decisions
Project management plan updates

Project document updates


Leave a Reply