How many risk response types are available for a negative risk event in the project?

You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your
project with your team. How many risk response types are available for a negative risk event in the
project?

PrepAway - Latest Free Exam Questions & Answers

A.
5

B.
7

C.
1

D.
4

Explanation:

Four risk response options are there to deal with negative risks or threats on the project
objectives- avoid, transfer, mitigate, and accept.
Risk avoidance
Risk mitigation
Risk transfer
Risk acceptance
available to deal with negative risks.