What are the various outputs of risk response?

What are the various outputs of risk response?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk Priority Number

B.
Residual risk

C.
Risk register updates

D.
Project management plan and Project document updates

E.
Risk-related contract decisions

Explanation:

The outputs of the risk response planning process are:
Risk Register Updates: The risk register is written in detail so that it can be related to the priority
ranking and the planned response.
Risk Related Contract Decisions: Risk related contract decisions are the decisions to transmit risk,
such as services, agreements for insurance, and other items as required. It provides a means for
sharing risks.
Project Management Plan Updates: Some of the elements of the project management plan
updates are:
Schedule management plan
Cost management plan
Quality management plan
Procurement management plan

Human resource management plan
Work breakdown structure
Schedule baseline
Cost performance baseline
Project Document Updates: Some of the project documents that can be updated includes:
Assumption log updates
Technical documentation updates
Answer B is incorrect. Residual risk is not an output of risk response. Residual risk is the risk that
remains after applying controls. It is not feasible to eliminate all risks from an organization.
Instead, measures can be taken to reduce risk to an acceptable level. The risk that is left is
residual risk.
As,
Risk = Threat Vulnerabilityand
Total risk = Threat Vulnerability Asset Value
Residual risk can be calculated with the following formula:
Residual Risk = Total Risk – Controls
Senior management is responsible for any losses due to residual risk. They decide whether a risk
should be avoided, transferred, mitigated or accepted. They also decide what controls to
implement. Any loss due to their decisions falls on their sides.
Residual risk assessments are conducted after mitigation to determine the impact of the risk on
the enterprise. For risk assessment, the effect and frequency is reassessed and the impact is
recalculated.
Answer A is incorrect. Risk priority number is not an output for risk response but instead it is done
before applying response. Hence it act as one of the inputs of risk response and is not the output
of it.