The only output of qualitative risk analysis is risk register updates. When the project manager

updates the risk register he will need to include several pieces of information including all of the
following except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Trends in qualitative risk analysis

B.
Risk probability-impact matrix

C.
Risks grouped by categories

D.
Watchlist of low-priority risks

Explanation:

The risk matrix is not included as part of the risk register updates. There are seven things that can
be updated in the risk register as a result of qualitative risk analysis: relating ranking of project
risks, risks grouped by categories, causes of risks, list of near-term risks, risks requiring additional
analysis, watchlist of low-priority risks, trends in qualitative risk analysis.
Answer C is incorrect. Risks grouped by categories are part of the risk register updates.
Answer D is incorrect. Watchlist of low-priority risks is part of the risk register updates.
Answer A is incorrect. Trends in qualitative risk analysis are part of the risk register updates.