PrepAway - Latest Free Exam Questions & Answers

which one of the following is an output of risk monitoring and control?

You are working as a project manager in Bluewell Inc.. You are nearing the final stages of project
execution and looking towards the final risk monitoring and controlling activities. For your project
archives, which one of the following is an output of risk monitoring and control?

PrepAway - Latest Free Exam Questions & Answers

A.
Qualitative risk analysis

B.
Risk audits

C.
Quantitative risk analysis

D.
Requested changes

Explanation:

Of all the choices given, only requested changes is an output of the monitor and control risks
process. You might also have risk register updates, recommended corrective and preventive
actions, organizational process assets, and updates to the project management plan.
Answer B is incorrect. Risk audit is a risk monitoring and control technique.