PrepAway - Latest Free Exam Questions & Answers

Which of following is the MOST likely action you should take?

You are the risk official of your enterprise. You have just completed risk analysis process. You
noticed that the risk level associated with your project is less than risk tolerance level of your
enterprise. Which of following is the MOST likely action you should take?

PrepAway - Latest Free Exam Questions & Answers

A.
Apply risk response

B.
Update risk register

C.
No action

D.
Prioritize risk response options

Explanation:

When the risk level is less than risk tolerance level of the enterprise than no action is taken against
that, because the cost of mitigation will increase over its benefits.
Answer D is incorrect. This is not valid answer, as no response is being applied to such low risk
level.
Answer B is incorrect. Risk register is updates after applying response, and as no response is
applied to such low risk level; hence no updating is done.
Answer A is incorrect. This is not valid answer, as no response is being applied to such low risk
level.


Leave a Reply