What are the key control activities to be done to ensure business alignment?

What are the key control activities to be done to ensure business alignment?
Each correct answer represents a part of the solution. Choose two.

PrepAway - Latest Free Exam Questions & Answers

A.
Define the business requirements for the management of data by IT

B.
Conduct IT continuity tests on a regular basis or when there are major changes in the IT
infrastructure

C.
Periodically identify critical data that affect business operations

D.
Establish an independent test task force that keeps track of all events

Explanation:

Business alignment require following control activities:
Defining the business requirements for the management of data by IT.
Periodically identifying critical data that affect business operations, in alignment with the risk
management model and IT service as well as the business continuity plan.
Answer B is incorrect. Conducting IT continuity tests on a regular basis or when there are major
changes in the IT infrastructure is done for testing IT continuity plan. It does not ensure alignment
with business.
Answer D is incorrect. This is not valid answer.